Contact UsFeedbackSitemapHome


Skip Navigation Links
 


Ahwaz Urban Railway Project

Widening and Strengthening of Andhra Pradesh State Highway (APSH9)

Planning System & Project Control of Tehran Metro, Lines 1&2 (Based on Two Contracts)

Drilling and Grouting Operations of the Tehran Metro Tunnel, Lines 1&2

Rehabilitation And Widening Of Bishkek-osh Road, Kyrgyzstan

Amir Kabir Underground Motorway

Yadegar Imam Flyover

Afsarieh Interchange

Khasab to Al-Khalidyeh Road Project







































Imam Khomeini International Airport, (phase 1) (Design and Build, “Fast-Track”)

In the past years
Client: Ministry of Roads & Transportation
Contract Period: 24 Months
Commencement Date: Oct. 1995
Type of Contract: Design-Build
Location: Tehran, Iran
   
Project Outline
The Imam Khomeini International Airport was an outstanding example of the impressive range of expertise that modern megaprojects demand: Project management and control, procurement, construction, and administration of the design and engineering subcontracts. Therefore, at the prequalification stage, Kayson had to prove its ability to plan, direct and manage this fast-track, multidisciplinary megaproject.

It is no wonder that Kayson has been recognized as one of the few construction and engineering firms in developing countries which possesses the resources and technological know-how necessary to build an international airport, and the government agency in charge of evaluating contracting and consulting engineering firms, the Management and Planning Organization, has assigned Kayson grade 1 (the highest ranking granted by that organization) in building transportation systems. One only has to take a look at the following facts and figures to get a true picture of the magnitude, complexity, and speed of execution of this megaproject:

The design and build contract between Kayson and the Ministry of Roads and Transportation was signed in Oct,1995.  
The first set of drawings were completed a month later
Construction of the terminal building started less than two months later.
Overall, 6000 sheets of drawings were prepared.
Over 25000 activities were supervised and controlled on a daily, weekly, and monthly basis.
Subcontract management involved 27 major consulting engineering and contracting firms, including the prominent French company, ADP.
500 cubic meters of concrete, 25 tonnes of reinforcement bars, and 100 tonnes of paving material were used each day.
138 design engineers and technicians labored to prepare the drawings, while 90 civil engineers and technicians, backed by a workforce of over 850 people and 300 pieces of construction equipment, worked virtually around the clock to put them into effect.


Main Features
Kayson's Scope of Work Included Engineering, Procurement, Construction and Commissioning of:
A 78,000 Square Meter Passenger Terminal
12,000 Square Meters of Service and Auxiliary Buildings
A 155,000 Square Meter Aircraft Maintenance Apron
A 4,200-Meter Long and 60-Meter Wide Runway
12,800 Meters of 45-Meter Wide Taxiways
27,500 Meters of 35-Meter Wide Access Roads n Nine Access Bridges for Motor Vehicles, and four Aircraft Taxiway Bridges.
Water Treatment Facilities and Distribution Networks
Fire-Fighting Facilities
Aircraft Refueling Network
Multi-Story Car Parking Facilities
Auxiliary Control Buildings, Loading Docks, and Storage Buildings.



 
 
 
 
   
   

 

 
Skip Navigation LinksHome > Projects > Examples of Projects > Imam Khomeini International Airport, (phase 1) (Design and Build, “Fast-Track”)
Copyright © 2010 Kayson Company. All rights reserved.