South Pars Field Development Project, Phases 2&3, Site Preparation
|
|
In the past years
Client: TOTAL
South Pars
Contract Period:
8 Months
Commencement Date:
Oct. 1998
Type of Contract:
Design-Build
Location:
Port of Assaluyeh, Iran
Partner: Bec
Freres of France |
|
 |
|
| |
|
Project Outline
In early October 1998, a contract was signed between
the prominent French company, TOTAL, and a joint venture of Kayson and
another French-based company, Bec Freres, (known as KAYSON INTERNATIONAL
JOINT VENTURE) to begin site development for a gas treatment facility
located near the Port of Assaluyeh in the Southern Iranian Province
of Boushehr.
The South Pars Field is being developed in multi phases,
each of which is based on an output level of at least one billion cubic
feet per day of natural gas and 40,000 barrels per day of associated
condensate.
The sphere of the work performed by the joint venture covered phases two
and three and included the actual site of the gas treatment facility,
the construction area where the prefabrication workshop for the gas
treatment plant will be located, and the camp area comprising office
space, sleeping quarters, a clinic, as well as storage and other
facilities.
Main Features
The TOTAL South Pars Gas Field Development
Project (Phases two & three) which encompassed an area of over 2.8
million square meters called for nearly 7 million cubic meters of
earthwork, 24 km of earth and concrete-lined culverts and channels. 12
km of fencing, 14.5 km of roads, 91,000 square meters of slope
protection, over 5000 square meters of office, living, storage and other
facilities- all to be completed within merely 8 months. To get the work
done on time, Kayson mobilized as many as 1300 workers laboring 10-hour
days and 350 pieces of light and heavy construction equipment operating
virtually around the clock.
|
|
|
|
|
|
|
|
|
|