Cut and consolidation operations, lower dam spillway berms
|
|
|
|
|
Formwork, extruded curb, upper dam
|
|
|
|
|
|
|
Rockfill, upper dam bottom
|
|
|
|
|
Reinforcement and formwork, lower dam plinth
|
|
|
|
|
Consolidation operation, lower dam left wing
|
|
|
|
|
Rockfill, lower dam bottom
|
|
|
|
|
Portal of access gallery to upper dam drainage tunnel
|
|
|
|
|
Portal of access gallery to lower dam drainage tunnel
|
|
|
|
|
Shotcrete and consolidation operations, upper dam
|
|
|
|
|
Concrete lining, left headrace tunnel
|
|
|
|
|
Foundation excavation, upper dam shaft silos
|
|
|
|
|
Excavation & concrete injection operations, upper dam
|
|
|
|
|
Concrete placement operations, upper dam bottom outlet
|
|
|