Al-Kifil Water Treatment Plant and Transmission Lines Project
Scope of Work:
Water Treatment Plant & Transmission pipe Line )Network), Including: detail design, purchasing of equipment, construction, installation and 1 Year operation and maintenance (EPC, Turn-Key)
Project Outline:
- Treatment Capacity: 4,000 m3/hr (88,000 m3/day)
- Population under Coverage: 560,000 People per day
Project Main Functions:
- Pipeline: 56 km
- Concrete: 19,500 m3
- Reinforcement: 2,000 t
- Formwork: 15,000 m2
- Administrative & auxiliary Building: 1,880 m2
- Earth work (lines & TP(: 193,000 m3