7200 Tonne/Day Saveh Gray Cement Plant, Production Lines

Project Outline

The Saveh grey cement factory is located 50 km from Saveh, a city in Markazi province in central Iran. Encompassing an area of 120 hectares, the plant is set to produce 7200 tonnes of cement per day, which can be increased to 8000 tonnes. Saveh grey cement factory is one of the most advanced cement producing plants in Iran, as well as the Middle East. Given the fact that over the past 20 years construction time for cement factories built in Iran has averaged 8 years or more, the Saveh factory is completed in 36 months (including civil & installation works), is destined to usher in a new era in Iran’s cement industry as far the speed of construction is concerned. The plant will also exceed national quality standards.

Limestone, the main raw material used in Saveh grey cement factory, is acquired from the huge Doshakh quarry located only 4 km away from the project site. Also, 400 hectares of uncultivated land surrounding the factory is devoted to planting trees, shrubs, and other greeneries, thus providing a pleasant scenery and minimizing the factory’s negative impacts on the environment.

Scope of Work

Kayson’s scope of work involved the civil works of Saveh grey cement factory’s production lines, including cut and fill operations, concrete pour of above and under-ground structures, limestone crushing plant, raw mill feed bunkers, raw mills, two nine-stage 110-meter high preheaters, coolers, ESP (electrostatic precipitator) dedusting units, cement silos, clinker silos, packing and loading plant, blending silos, masonry work, building construction, structural steelwork, etc.

Key Statistics

  • Concrete: 145,000 m3
  • Reinforcement: 18,000 t
  • Formwork: 250,000 m2
  • Heavy steelwork: 4000 t
  • Earthwork: 220,000 m3

Photo Gallery

Main Related Projects:

  • Sangan 2.5 MTPY Iron Ore Concentration Plant
    Sangan 2.5 MTPY Iron Ore Concentration Plant
  • Civil Works and Mechanical Instalation Works of Sabalan Petrochemical Projects
    Civil Works and Mechanical Instalation Works of Sabalan Petrochemical Projects
  • Gol-E-Gohar Pelletizing Plant II
    Gol-E-Gohar Pelletizing Plant II
  • South Pars Gas Field Development – Phase 12 Onshore Facilities Liquid Processing and Utilities (EPC 2)
    South Pars Gas Field Development – Phase 12 Onshore Facilities Liquid Processing and Utilities (EPC 2)
  • 4TH Aromatics Plant, Process Area
    4TH Aromatics Plant, Process Area
  • South Pars, Phases 4&5, Site Preparation
    South Pars, Phases 4&5, Site Preparation
  • Aghajari Gas Injection Project
    Aghajari Gas Injection Project
  • Neka-Ray Crude-Oil Pipeline Pumping Stations and Related Installations
    Neka-Ray Crude-Oil Pipeline Pumping Stations and Related Installations
  • South Pars Field Development Project, Phases 2&3, Site Preparation
    South Pars Field Development Project, Phases 2&3, Site Preparation
  • Almahdi Aluminum Complex (8 Separate Contracts)
    Almahdi Aluminum Complex (8 Separate Contracts)
  • Aliabad Katoul-Shahrood 70 Km, 16” Gas Pipeline
    Aliabad Katoul-Shahrood 70 Km, 16” Gas Pipeline
  • لوگو پرگار وب
    طراحی سایت و سئو سایت توسط پرگار وب