Construction Work of Sangmelima – Mekok – Bikoula (65 Km. Road) in Republic of Cameroon
Project Outline
Construction works of the Sangmelima – Ouesso road, Lot 1: Sangmelima – Djoum, Section 1: Sangmelima – Mekok – Bikoula (65 km), Situated in the Dja et Lobo Division, south region.
Scope of Works
Road Component:
- Site installation
- Construction studies
- Preparatory works
- Earthworks
- Execution of a 7.5 m wide carriageway with 2×2 m double surface paved shoulders each in build-up areas
The carriageway structure comprises the following:
– Construction of drainage structures (concrete box and ring culverts, slaps, ditches, etc.)
– Construction of bridges
– Realization of road equipment, signing and marking
– Construction of a weighing station for heavy duty vehicles, including a parking area of 50,000 m2
– Construction of a weighing station between Sangmelima and Djoum
– Installation of an automatic metering post
– Implementation of road protection measures
Drainage Structures Component:
- The works consist of the construction of five 2 × (2.5 m × 2.5 m) double slaps and 3 triple 3 × (2.5 m × 2.5 m) slaps.
- Characteristics common to the major slaps:
– Carriageway width: 7.50 m
– Shoulder width: 2 × 1.50 m